Monday, February 24, 2014

Tile and Wood

Tile has been working hard this past week. YAY! We have tile in the kitchen, hallway, laundry room, powder bathroom, and craft room. They are nearly done with the floor everywhere. They also started and finished the backsplash! 

And as of this morning they were grouting the backsplash and the floor that they had done! 

Starting to really look like a kitchen! 


They also did the white subway tile backsplash in the laundry room!



The wood guys actually came and started a couple days. 

And the master bath....... Still working in that pesky shower! And finally starting on the tub deck and walls. Still no tile on the floor in the master bath!



Small steps!

Monday, February 17, 2014

Accepting the Facts

Gosh, it's hard accepting the facts that the move in date keeps getting pushed farther back. I mean there is no "move in date" per say, but when no one cracks the door of the house for 6 days, working days, it's not likely you are going to move in soon. I just don't understand the building process. One thing I do know is it is full of lies. 

So, this weekend, we had to accept the cold, hard facts, again, that it is just not even possible that we will be in the first of March. With that being said, it causes some problems with us needing to go ahead and move out, so Jason's brother can move in. Where do we go? How long will we actually have to be there until it's done? This means we have to move our stuff TWICE. 

Luckily, things are going to work out for us to stay in our house one more month. That's what it's been for a while now, just one more month. 

The good thing is the kids don't have a clue of all this stress, and are just happy go lucky with everything. Which reminds me, I just need to let it go.

Both kids bathrooms showers and floors completely done and GROUTED! For some reason, adding the grout makes it just look so much prettier!! 

Ready for toilets!! :) And the base boards still need to be painted. 


The lady glazing all the cabinets is pretty much done. She finished in the laundry room, and just has to come back to touch up. It looks so good. I'm telling you, the laundry room is going to be fancy, smancy with a chandelier and everything!

Saturday, February 8, 2014

Tile Progress & More

Jaxon's Bathroom and the girls bathroom tile floor and showers are all done! Everything is glued down; now, they just need to grout it! 


The master shower and bathroom is quite the hold up. Why? I don't even know. Seriously, hardly any progress to report after a week. :(


The playroom is striped!! I love it! And a ceiling fan!! Yay!



But, other progress was made. The security system and air conditioners units were put in!!


What's left?
1. Finish tiling master bathroom, and kitchen floors.
2. Wood floors and carpet floors.
3. Paint the trim outside, and stain the decking outside. 
4. pour concrete sidewalks/driveway outside. 
5. Install the propane tank. 
6. Rock the Vent-a-Hood in the kitchen. 
7. Paint the baseboards, and touch-ups inside. 
8. Paint the garage. 
9. Glaze the Laundry Room cabinets. 
10. Put Hardware on. 
11. Install appliances. 
12. Finish hanging lighting fixtures. 
13. Measure and install mirrors for bathrooms. 
14. Lay wallpaper in powder bathroom. 
15. Do some landscaping. 

Can it be done in 3 weeks? :)

Tuesday, February 4, 2014

Moving On

I wish we were moving IN, but we are just moving on with a little more progress. 

The painters are pretty much done; they will come back after floors are in, and do the baseboards, touch ups, and paint the dining room. There is still outside painting to be done also. 

A lady that lives here does some glazing, striping, or any other kind of special paint job that you want. 

So, she did the girls bathroom glazed, and she did these glossy stripes in Kylee's room. I like how they turned out! 

And she is also going to do horizontal stripes in the kids playroom! Excited to see that finished!! 


They delivered lights and fans!!


And they put them up!!!


The tile guys are here working too!! I would be excited, but it is just going so slow! They are trying to finish the master shower and Jaxon's shower, and start on the master tub. 

There's just a long way to go on the floors..... That being said they did deliver the floor tile!!